PWS ID:
00240 ---- RIVERSTONE MOBILE HOME PARK
Compliance and Enforcement Schedules
Schedule Type: All Groups
Schedule Status: Open and Closed Schedules
Type of Action |
Status |
Date Issued |
Due Date |
Closed Date |
Lead Action Level Exceedance |
|
Jul 12, 2022 |
| Open |
DISTRIBUTION WATER QUALITY PARAMETERS |
| Aug 22, 2022 |
Sep 01, 2022 - Late |
ENTRY POINT WATER QUALITY PARAMETERS |
| Aug 22, 2022 |
Sep 01, 2022 - Late |
ISSUE LCR PUBLIC EDUCATION |
| Dec 10, 2022 |
Jan 04, 2023 - Late |
ENTRY POINT LEAD/COPPER SAMPLE |
| Mar 31, 2023 |
Sep 01, 2022 |
SUBMIT RECOMMENDATION FOR LCR TREATMENT |
| Mar 31, 2023 |
Mar 17, 2023 |
SUBMIT PLANS FOR TREATMENT |
| Sep 30, 2024 |
|
INSTALL CORROSION CONTROL TREATMENT |
| Mar 31, 2025 |
|
Confirmed Source E. coli |
|
May 01, 2019 |
| Aug 30, 2019 |
ISSUE PUBLIC NOTICE |
| May 15, 2019 |
May 03, 2019 |
CORRECT ALL DEFICIENCIES/SUBMIT PLAN-CO |
| Sep 04, 2019 |
Aug 30, 2019 |