Type of Action Date Issued Due Date Closed Date
Other Compliance Schedule Jun 01, 2017   Dec 27, 2017
LCR M&R  Oct 10, 2017 Dec 27, 2017 - Late
Administrative Order Apr 20, 2017   Sep 06, 2018
ARSENIC M&R  May 10, 2017 Apr 19, 2017
SUBMIT PLAN  Jun 05, 2017 Jun 05, 2017
ARSENIC M&R  Jun 10, 2017 May 17, 2017
ISSUE PUBLIC NOTICE  Jul 10, 2017 Apr 28, 2017
ARSENIC M&R  Jul 10, 2017 Jun 15, 2017
ARSENIC M&R  Aug 10, 2017 Jul 14, 2017
ARSENIC M&R  Sep 10, 2017 Aug 22, 2017
ARSENIC M&R  Oct 10, 2017 Sep 15, 2017
ISSUE PUBLIC NOTICE  Oct 10, 2017 Oct 10, 2017
ARSENIC M&R  Nov 10, 2017 Oct 26, 2017
ARSENIC M&R  Dec 10, 2017 Nov 17, 2017
ARSENIC M&R  Jan 10, 2018 Dec 29, 2017
ISSUE PUBLIC NOTICE  Jan 10, 2018 Jan 04, 2018
ARSENIC M&R  Feb 10, 2018 Jan 25, 2018
ARSENIC M&R  Mar 10, 2018 Feb 27, 2018
ARSENIC M&R  Apr 10, 2018 Mar 23, 2018
ISSUE PUBLIC NOTICE  Apr 10, 2018 Apr 09, 2018
ARSENIC M&R  May 10, 2018 Apr 12, 2018
ARSENIC M&R  Jun 10, 2018 May 11, 2018
ARSENIC M&R  Jul 10, 2018 Jun 28, 2018
ISSUE PUBLIC NOTICE  Jul 10, 2018 Jul 03, 2018
ARSENIC M&R  Aug 10, 2018 Jul 23, 2018
ARSENIC M&R  Sep 01, 2018 Aug 27, 2018
CORRECT WATER QUALITY DEFICIENCIES  Sep 01, 2018 Aug 27, 2018
ISSUE PUBLIC NOTICE  Oct 10, 2018 Sep 06, 2018
Response to Significant Deficiency Oct 24, 2014   Dec 17, 2015
CORRECTIVE ACTION PLAN SUBMITTED   May 21, 2015
CORRECT ALL DEFICIENCIES/SUBMIT PLAN- GW  Jun 26, 2015 May 21, 2015
CORRECTIVE ACTION PLAN DUE DATE - GW  Dec 31, 2015 Dec 17, 2015
Bilateral Compliance Agreement Jun 12, 2014   Sep 18, 2015
COMPLETE CONSTRUCTION  Jun 30, 2015 May 28, 2015
CORRECT WATER QUALITY DEFICIENCIES  Dec 31, 2015 Sep 18, 2015
Other Agency Document Sep 12, 2013   Jun 12, 2014
COMPLETE CONSTRUCTION  Apr 30, 2014 Overdue
CORRECT WATER QUALITY DEFICIENCIES  Jun 30, 2014 Overdue
Bilateral Compliance Agreement Mar 15, 2012   Sep 12, 2013
ISSUE PUBLIC NOTICE  Apr 10, 2012 Feb 08, 2012
ARSENIC M&R  Jul 10, 2012 Apr 19, 2012
ISSUE PUBLIC NOTICE  Jul 10, 2012 Jun 01, 2012
COMPLETE CONSTRUCTION  Sep 30, 2012 Overdue
ARSENIC M&R  Oct 10, 2012 Aug 09, 2012
ISSUE PUBLIC NOTICE  Oct 10, 2012 Sep 26, 2012
CORRECT WATER QUALITY DEFICIENCIES  Dec 30, 2012 Overdue
Bilateral Compliance Agreement Jul 02, 2010   Mar 15, 2012
PLAN REVIEW  Sep 30, 2010 Dec 20, 2010 - Late
ARSENIC M&R  Jan 10, 2011 Dec 22, 2010
ISSUE PUBLIC NOTICE  Jan 10, 2011 Jan 19, 2011 - Late
COMPLETE CONSTRUCTION  Sep 30, 2011 Overdue
CORRECT WATER QUALITY DEFICIENCIES  Mar 31, 2012 Overdue


For all compliance errors please phone Brad Daniels, DWS Compliance Specialist, at 971-673-0405.



For further information on this public water system, click on the area of interest below:
System Info :: Report for Lenders :: Alerts :: Violations :: Compliance & Enforcement :: Contacts & Advisories :: Site Visits :: Public Notice
Coliform Summary :: Coliform Results :: Sampling Schedule for Coliform :: Groundwater/GWUDI Source Details :: Plan Review :: Annual Fee
Chemical Group Summary :: Latest Chemical Results :: Entry Point Detects :: Single Analyte Results 
Chemical Schedule Summary :: Chemical Schedule Details
Lead & Copper :: Corrosion Control (LCR) :: Nitrate :: Arsenic :: Radionuclides :: GWR 4-Log :: LT2 :: Cyanotoxins
DBPs :: TOC & Alkalinity :: DBP Sample Sites :: FANLs :: MRDL :: Turbidity :: SWTR :: RAA :: LRAA