PWS ID:
00789 ---- SANDY, CITY OF
Compliance and Enforcement Schedules
Schedule Type: All Groups
Schedule Status: Open and Closed Schedules
Type of Action |
Status |
Date Issued |
Due Date |
Closed Date |
Bilateral Compliance Agreement |
|
Jan 22, 2020 |
| Open |
Bilateral Compliance Agreement |
|
Sep 21, 2018 |
| Open |
SUBMIT COMPLIANCE ACTION PLAN |
| Mar 30, 2020 |
Mar 20, 2020 |
SUBMIT MASTER PLAN |
| Dec 30, 2020 |
Dec 07, 2022 - Late |
BEGIN CONSTRUCTION |
| Jul 31, 2024 |
|
CORRECT WATER QUALITY DEFICIENCIES |
| Sep 30, 2027 |
|
Other Compliance Schedule |
|
Jan 18, 2022 |
| Jan 19, 2022 |
SUBMIT OPERATIONAL EVALUATION REPORT |
| |
Jan 19, 2022 |
Bilateral Compliance Agreement |
|
Apr 07, 2016 |
| Jul 06, 2018 |
SUBMIT PLAN |
| Jun 30, 2016 |
Jun 30, 2016 |
ISSUE PUBLIC NOTICE |
| Jul 10, 2016 |
Jun 03, 2016 |
ISSUE PUBLIC NOTICE |
| Apr 10, 2017 |
Feb 28, 2017 |
SUBMIT CONSTRUCTION PLAN |
| Jun 30, 2017 |
Apr 23, 2018 - Late |
ISSUE PUBLIC NOTICE |
| Jul 10, 2017 |
Nov 20, 2017 - Late |
ISSUE PUBLIC NOTICE |
| Oct 10, 2017 |
Aug 28, 2017 |
ISSUE PUBLIC NOTICE |
| Jan 10, 2018 |
Feb 15, 2018 - Late |
ISSUE PUBLIC NOTICE |
| Apr 10, 2018 |
Feb 13, 2018 |
REPORT DBP MONITORING |
| Apr 10, 2018 |
Feb 13, 2018 |
REPORT DBP MONITORING |
| Jul 10, 2018 |
Jul 06, 2018 |
COMPLETE CONSTRUCTION |
| Dec 31, 2018 |
Apr 23, 2018 |
Response to Significant Deficiency |
|
Nov 05, 2014 |
| Apr 06, 2015 |
CORRECT ALL DEFICIENCIES/SUBMIT PLAN- SW |
| Apr 08, 2015 |
Apr 06, 2015 |
Other Agency Document |
|
|
| Apr 02, 2021 |
SUBMIT OPERATIONAL EVALUATION REPORT |
| |
Apr 02, 2021 |