Type of Action |
Status |
Date Issued |
Due Date |
Closed Date |
Administrative Order |
|
Feb 28, 2023 |
| Open |
ISSUE PUBLIC NOTICE |
| Mar 10, 2023 |
Mar 15, 2023 - Late |
ALLOW SITE VISIT BY REGULATOR |
| Mar 30, 2023 |
Mar 10, 2023 |
REPORT COLIFORM MONITORING |
| Apr 10, 2023 |
Mar 10, 2023 |
REPORT COLIFORM MONITORING |
| May 10, 2023 |
Apr 17, 2023 |
REPORT SOURCE WATER COLIFORM MONITORING |
| Jun 10, 2023 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Jul 10, 2023 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Aug 10, 2023 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Sep 10, 2023 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Oct 10, 2023 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Nov 10, 2023 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Dec 10, 2023 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Jan 10, 2024 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Feb 10, 2024 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Mar 10, 2024 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| Apr 10, 2024 |
|
REPORT SOURCE WATER COLIFORM MONITORING |
| May 10, 2024 |
|
Coliform Investigation |
|
Jan 23, 2023 |
| Mar 10, 2023 |
LEVEL 2 INVESTIGATION - NO REPEATS |
| Feb 25, 2023 |
Mar 10, 2023 - Late |
Coliform Investigation |
|
Dec 27, 2022 |
| Mar 10, 2023 |
LEVEL 2 INVESTIGATION - NO REPEATS |
| Jan 26, 2023 |
Mar 10, 2023 - Late |
Coliform Investigation |
|
Oct 19, 2022 |
| Mar 10, 2023 |
COMPLETE LEVEL 2 INVESTIGATION |
| Dec 01, 2022 |
Mar 10, 2023 - Late |
Coliform Investigation |
|
Aug 10, 2021 |
| Mar 10, 2023 |
LEVEL 2 INVESTIGATION - NO REPEATS |
| Sep 12, 2021 |
Mar 10, 2023 - Late |
Coliform Investigation |
|
Jul 15, 2020 |
| Mar 10, 2023 |
COMPLETE LEVEL 1 INVESTIGATION |
| Aug 22, 2020 |
Mar 10, 2023 - Late |
Coliform Investigation |
|
May 26, 2020 |
| Mar 10, 2023 |
LEVEL 2 INVESTIGATION - NO REPEATS |
| Jun 27, 2020 |
Mar 10, 2023 - Late |
Coliform Investigation |
|
Apr 21, 2020 |
| Mar 10, 2023 |
LEVEL 2 INVESTIGATION - NO REPEATS |
| May 23, 2020 |
Mar 10, 2023 - Late |
Coliform Investigation |
|
Oct 21, 2019 |
| Mar 10, 2023 |
LEVEL 2 INVESTIGATION - NO REPEATS |
| Nov 23, 2019 |
Mar 10, 2023 - Late |
Coliform Investigation |
|
Jul 22, 2019 |
| Aug 14, 2019 |
COMPLETE LEVEL 2 INVESTIGATION |
| Aug 24, 2019 |
Aug 14, 2019 |
Coliform Investigation |
|
Nov 26, 2018 |
| Dec 27, 2018 |
LEVEL 2 INVESTIGATION - NO REPEATS |
| Dec 29, 2018 |
Dec 27, 2018 |
Coliform Investigation |
|
Oct 09, 2018 |
| Dec 27, 2018 |
LEVEL 1 INVESTIGATION - NO REPEATS |
| Nov 11, 2018 |
Dec 27, 2018 - Late |
Coliform Investigation |
|
Nov 14, 2017 |
| Nov 24, 2017 |
COMPLETE LEVEL 1 INVESTIGATION |
| Dec 23, 2017 |
Nov 24, 2017 |
Coliform Investigation |
|
Jun 14, 2016 |
| Sep 19, 2016 |
COMPLETE LEVEL 1 INVESTIGATION |
| Jul 14, 2016 |
Jul 11, 2018 - Late |
Response to Significant Deficiency |
|
Oct 21, 2014 |
| Sep 26, 2018 |
CORRECT ALL DEFICIENCIES/SUBMIT PLAN- GW |
| Feb 21, 2015 |
Sep 26, 2018 - Late |
Bilateral Compliance Agreement |
|
Jul 25, 2012 |
| Jul 10, 2013 |
REPORT IOC MONITORING |
| Aug 10, 2012 |
Jul 24, 2012 |
ISSUE LCR PUBLIC EDUCATION |
| Aug 10, 2012 |
Jul 31, 2012 |
REPORT LEAD & COPPER TAP MONITORING |
| Aug 31, 2012 |
Jul 24, 2012 |
COMPLETE MONITORING |
| Aug 31, 2012 |
Aug 31, 2012 |
REPORT VOC MONITORING |
| Sep 10, 2012 |
Jul 24, 2012 |
REPORT SOC MONITORING |
| Sep 10, 2012 |
Aug 13, 2012 |
CORRECT SIGNIFICANT DEFCIENCIES |
| Oct 31, 2012 |
May 14, 2013 - Late |
REPORT LEAD & COPPER TAP MONITORING |
| Jul 10, 2013 |
Jul 10, 2013 |