Administrative Order |
May 26, 2022 |
| Open | Administrative Order |
Open |
ISSUE PUBLIC NOTICE |
|
Jul 10, 2022 |
Aug 8, 2022 - Late
| Administrative Order |
Open |
SUBMIT CORRECTIVE ACTION PLAN |
|
Jul 31, 2022 |
Jul 12, 2022
| Administrative Order |
Open |
SUBMIT COMPLIANCE ACTION PLAN |
|
Oct 31, 2022 |
Oct 31, 2022
| Administrative Order |
Open |
SUBMIT CONSTRUCTION PLAN |
|
Feb 28, 2023 |
Feb 15, 2023
| Administrative Order |
Open |
SUBMIT SDWRLF LETTER OF INTENT |
|
Mar 15, 2023 |
Sep 13, 2023 - Late
| Administrative Order |
Open |
BEGIN CONSTRUCTION |
|
Dec 31, 2027 |
| Administrative Order |
Open |
COMPLETE FACILITY OR SYSTEM STARTUP |
|
Jun 30, 2028 |
| Administrative Order |
Open |
REPORT SURFACE WATER TREATMENT |
|
Aug 10, 2028 |
| Administrative Order |
Open |
Administrative Order |
Jan 24, 1992 |
| Aug 4, 2003 | Administrative Order |
Closed |