| Confirmed Source E. coli |
Aug 4, 2020 |
| Open | Confirmed Source E. coli |
Open |
| CORRECT ALL DEFICIENCIES/SUBMIT PLAN-CO |
|
Dec 4, 2020 |
Nov 30, 2020 | Confirmed Source E. coli |
Open |
| SUBMIT CORRECTIVE ACTION PLAN |
|
Jan 1, 2023 |
Feb 22, 2023 - Late | Confirmed Source E. coli |
Open |
| SUBMIT CONSTRUCTION PLAN |
|
Apr 30, 2023 |
May 9, 2023 - Late | Confirmed Source E. coli |
Open |
| COMPLETE CONSTRUCTION |
|
Apr 1, 2024 |
Overdue | Confirmed Source E. coli |
Open |
| Microscopic Particulate Analysis (MPA) Required |
Nov 23, 2020 |
| Sep 17, 2021 | Microscopic Particulate Analysis (MPA) Required |
Closed |
| REPORT MPA SAMPLE(S) |
|
Sep 15, 2021 |
Sep 17, 2021 - Late | Microscopic Particulate Analysis (MPA) Required |
Closed |