| Lead Action Level Exceedance |
Sep 30, 2024 |
| Open | Lead Action Level Exceedance |
Open |
| DISTRIBUTION WATER QUALITY PARAMETERS |
|
Nov 12, 2024 |
Overdue | Lead Action Level Exceedance |
Open |
| ENTRY POINT WATER QUALITY PARAMETERS |
|
Nov 12, 2024 |
Overdue | Lead Action Level Exceedance |
Open |
| ISSUE LCR PUBLIC EDUCATION |
|
Dec 10, 2024 |
Oct 2, 2025 - Late | Lead Action Level Exceedance |
Open |
| SUBMIT RECOMMENDATION FOR LCR TREATMENT |
|
Mar 31, 2025 |
Overdue | Lead Action Level Exceedance |
Open |
| ENTRY POINT LEAD/COPPER SAMPLE |
|
Mar 31, 2025 |
Mar 24, 2025 | Lead Action Level Exceedance |
Open |
| SUBMIT PLANS FOR TREATMENT |
|
Sep 30, 2026 |
| Lead Action Level Exceedance |
Open |
| INSTALL CORROSION CONTROL TREATMENT |
|
Mar 31, 2027 |
| Lead Action Level Exceedance |
Open |
| Lead Action Level Exceedance |
Jul 22, 2016 |
| Dec 20, 2017 | Lead Action Level Exceedance |
Closed |
| DISTRIBUTION WATER QUALITY PARAMETERS |
|
Sep 2, 2016 |
Oct 1, 2016 - Late | Lead Action Level Exceedance |
Closed |
| ENTRY POINT WATER QUALITY PARAMETERS |
|
Sep 2, 2016 |
Oct 1, 2016 - Late | Lead Action Level Exceedance |
Closed |
| ISSUE LCR PUBLIC EDUCATION |
|
Dec 10, 2016 |
Aug 25, 2016 | Lead Action Level Exceedance |
Closed |
| ENTRY POINT LEAD/COPPER SAMPLE |
|
Mar 31, 2017 |
Apr 5, 2017 - Late | Lead Action Level Exceedance |
Closed |
| SUBMIT RECOMMENDATION FOR LCR TREATMENT |
|
Mar 31, 2017 |
May 8, 2017 - Late | Lead Action Level Exceedance |
Closed |
| 2 FOLLOW-UP ROUNDS BELOW AL |
|
Jan 10, 2018 |
Dec 20, 2017 | Lead Action Level Exceedance |
Closed |
| COMPLETE PLUMBING REPLACEMENT PROGRAM |
|
Mar 31, 2018 |
May 8, 2017 | Lead Action Level Exceedance |
Closed |
| Other Compliance Schedule |
Jun 6, 2016 |
| Jul 9, 2016 | Other Compliance Schedule |
Closed |
| REPORT LEAD & COPPER TAP MONITORING |
|
Oct 10, 2016 |
Jul 9, 2016 | Other Compliance Schedule |
Closed |
| Other Compliance Schedule |
Aug 27, 2014 |
| Jan 7, 2015 | Other Compliance Schedule |
Closed |
| CORRECT WATER QUALITY DEFICIENCIES |
|
Sep 26, 2014 |
Sep 23, 2014 | Other Compliance Schedule |
Closed |
| CORRECTIVE ACTION PLAN SUBMITTED |
|
Sep 26, 2014 |
Sep 23, 2014 | Other Compliance Schedule |
Closed |
| CORRECTIVE ACTION PLAN DUE DATE - GW |
|
Oct 31, 2014 |
Jan 7, 2015 - Late | Other Compliance Schedule |
Closed |