Plan ID | Project Name |
Date All Received |
Request for Additional Info |
Site Plan Evaluation/ Approval |
Conditional Approval |
Preliminary Approval |
Date Abandoned |
Final Approval |
Reviewer |
---|---|---|---|---|---|---|---|---|---|
98-2018 | Transmission Line | 07/30/2018 | 08/23/2018 | 06/04/2020 | BG | ||||
64-2017 | arsenic treatment | 06/06/2017 | 06/05/2017 | 06/04/2020 | BG | ||||
94-2014 | New Well | 06/17/2014 | 06/12/2014 | 06/17/2014 | 06/04/2020 | BG | |||
140-2013 | Master Plan | 10/03/2013 | 09/27/2013 | 09/27/2013 | 10/03/2013 | BG | |||
155-2005 | New Well #5 l66040 /Transmission line | 06/16/2005 | 06/17/2005 | 06/17/2005 | 09/26/12 | BG | |||
193-2002 | Master Plan | 08/30/2002 | 12/06/2002 | GB | |||||