| Most Recent Water System Survey |
| Survey Date: |
Dec 04, 2025 |
| Notification Date: |
Dec 30, 2025 (26 days) |
| Regulating Agency: |
DWS (REGION 2) |
| Survey Frequency: |
3 YR - Visit the Water System Surveys page to see the list of surveys due each year. |
| Deficiencies: |
| Category |
Deficiency |
Due Date |
Resolved Date |
| Finished Water Storage |
No flap valve, screen, or equivalent on overflow | Feb 17, 2026 |
|
| Operator Certification |
No protocol for under-certified operator | Feb 17, 2026 |
|
| Treatment |
No physical separation between treated and untreated water | Feb 17, 2026 |
|
| Surface Water Treatment |
Incorrect location for compliance turbidity monitoring | Feb 17, 2026 |
|
| Surface Water Treatment |
For conventional or direct filtration: No alarm or plant shut off for high turbidity | Feb 17, 2026 |
|
| Surface Water Treatment |
For conventional or direct filtration: Turbidity profile not conducted on individual filters at least quarterly | Feb 17, 2026 |
|
| Disinfection |
Chlorine not measured & recorded as required | Feb 17, 2026 |
Dec 04, 2025
|
| Surface Water Treatment |
For conventional filtration: Settled water not measured daily | Feb 17, 2026 |
Jan 06, 2026
|
Bold text indicates that resolving this deficiency is a top priority.
|
| Water System Site Visit History |
| Reason |
Visit Date |
Frequency |
Next Due |
Notification Date (Days after survey) |
Responsible Agency |
Comments and Deficiencies |
| Sanitary Survey, Finished (SNSV) |
12/04/2025 |
3 YR |
* |
12/30/2025 (26) |
REGION 2 |
Hide details |
| |
| Category |
Deficiency |
Due Date |
Resolved Date |
| Finished Water Storage |
No flap valve, screen, or equivalent on overflow | Feb 17, 2026 |
|
| Operator Certification |
No protocol for under-certified operator | Feb 17, 2026 |
|
| Treatment |
No physical separation between treated and untreated water | Feb 17, 2026 |
|
| Surface Water Treatment |
Incorrect location for compliance turbidity monitoring | Feb 17, 2026 |
|
| Surface Water Treatment |
For conventional or direct filtration: No alarm or plant shut off for high turbidity | Feb 17, 2026 |
|
| Surface Water Treatment |
For conventional or direct filtration: Turbidity profile not conducted on individual filters at least quarterly | Feb 17, 2026 |
|
| Disinfection |
Chlorine not measured & recorded as required | Feb 17, 2026 |
Dec 04, 2025 |
| Surface Water Treatment |
For conventional filtration: Settled water not measured daily | Feb 17, 2026 |
Jan 06, 2026 |
|
| Sanitary Survey, Finished (SNSV) |
11/17/2022 |
3 YR |
* |
12/20/2022 (33) |
REGION 2 |
Show details |
| Water Treatment Plant Site Visit (TRTP) |
11/16/2022 |
3 YR |
11/16/2025 |
12/20/2022 (34) |
REGION 2 |
No details |
| Sanitary Survey, Finished (SNSV) |
07/28/2017 |
5 YR |
* |
07/28/2017 (0) |
REGION 1 |
Show details |
| Water Treatment Plant Site Visit (TRTP) |
07/28/2017 |
3 YR |
07/28/2020 |
07/28/2017 (0) |
REGION 1 |
No details |
| Sanitary Survey, Finished (SNSV) |
04/03/2012 |
5 YR |
* |
09/07/2012 (157) |
REGION 2 |
Show details |
| Water Treatment Plant Site Visit (TRTP) |
04/03/2012 |
5 YR |
04/03/2017 |
09/07/2012 (157) |
REGION 2 |
No details |
| Sanitary Survey, Finished (SNSV) |
09/22/2009 |
1 YR |
* |
10/23/2009 (31) |
REGION 2 |
Show details |
| Water Treatment Plant Site Visit (TRTP) |
09/22/2009 |
3 YR |
09/22/2012 |
10/23/2009 (31) |
REGION 2 |
Show details |
| Water Treatment Plant Site Visit (TRTP) |
11/09/2005 |
3 YR |
11/09/2008 |
01/09/2006 (61) |
REGION 2 |
Show details |
| Sanitary Survey, Finished (SNSV) |
11/08/2005 |
3 YR |
* |
|
REGION 2 |
Show details |
| Water Treatment Plant Site Visit (TRTP) |
11/08/2005 |
3 YR |
11/08/2008 |
01/09/2006 (62) |
REGION 2 |
Show details |
| |